This document provides a structured technical specification for the EPC delivery of HV/MV substations in Serbia under Clarion Engineers’ (clarion.engineer) engineering, QA/QC, and grid-compliance framework.
Part 1 — General Requirements
1.1 Scope of Work
This specification covers the design, procurement, manufacture, delivery, installation, testing, commissioning, energization, and handover of a 110/35/20/10 kV HV/MV substation in Serbia, including:
-
Primary equipment (transformers, switchgear, busbars, disconnectors, instrument transformers)
-
Secondary systems (protection, control, automation, SCADA, metering)
-
Civil works (foundations, structures, fencing, drainage, trenches, control building)
-
Grid-connection compliance (EMS / DSO requirements)
-
Integration with plant SCADA and dispatch centres
-
Commissioning, reliability testing, and performance guarantees
EPC delivery is full turnkey, single-point responsibility.
Part 2 — Codes, Standards & Compliance
2.1 Relevant Standards
Substation must comply with:
-
Serbian grid code requirements
-
IEC HV/MV standards
-
EU safety, EMC, and environmental directives
-
Clarion QA/QC, ITP and HSE frameworks
The most stringent rule always applies.
Part 3 — System Design Requirements
3.1 Single-Line Diagram (SLD)
EPC must provide:
-
Full SLD (HV/MV/LV)
-
Busbar configuration
-
Transformer connections
-
Protection zones
-
Earthing and fault current studies
3.2 Rated Parameters
Typical Serbian substation ratings:
| Voltage Level | 110 kV | 35 kV | 20 kV | 10 kV |
|---|---|---|---|---|
| Frequency | 50 Hz | 50 Hz | 50 Hz | 50 Hz |
| Short-circuit level | 31.5–40 kA | 20–31.5 kA | 16–25 kA | 16–25 kA |
Actual values must be confirmed with EMS/DSO.
Part 4 — Primary Equipment Specification
4.1 Power Transformers
Ratings:
110/x kV, 20–40 MVA typical
ONAN/ONAF cooling
Vector groups per grid code
OLTC ±10–16%
Requirements:
Oil: inhibited mineral or ester
Cooling control & fans
Online monitoring (temperature, gas, moisture)
Buchholz relay
Oil level, PRD, winding/oil temp
EU efficiency-class compliance
4.2 High-Voltage Switchgear (110 kV)
Options: GIS or AIS
Minimum 31.5 kA short-circuit
SF₆ monitoring (GIS)
Motorized disconnectors
Interlocking schemes
IEC 61850-ready
4.3 Medium-Voltage Switchgear (35/20/10 kV)
Metal-clad, withdrawable
Vacuum breakers
Internal arc classification AFLR
Busbar segregation
SCADA integration
CT/PT compartments
4.4 Instrument Transformers
Accuracy per metering/protection class
Oil-filled or cast resin
Insulation levels per Serbian category
4.5 Surge Arresters & Earthing
Metal-oxide arresters
Grounding system design including:
step/touch limits, resistance criteria, and lightning protection.
Part 5 — Secondary Systems Specification
5.1 Protection & Control
Protection functions include:
-
Transformer differential (87T)
-
Distance/line protection (21/21N)
-
Overcurrent (50/51/50N/51N)
-
Busbar protection (GIS optional)
-
Breaker failure (50BF)
-
Auto-reclosing
-
Backup zones
Requirements:
Redundant CPUs
Dual communication channels
GPS/IRIG-B time sync
Disturbance recorder
IEC 61850-native devices
5.2 SCADA & Automation
EPC must deliver:
-
Local HMI
-
Dispatch centre connectivity
-
IEC 61850 / 60870-5-104 protocols
-
Cybersecurity (firewalls, VLANs, access control)
-
Event and disturbance logs
-
Historian
5.3 Metering
Revenue metering (import/export)
Accuracy: Class 0.2S
Utility-approved metering panels
Integration to TSO/DSO gateway
Part 6 — Civil & Structural Works
Includes:
-
Control building
-
Transformer foundations & bunds
-
GIS/AIS platforms
-
Cable trenches & ducts
-
Fencing
-
Access roads
-
Stormwater drainage
-
Fire protection
-
Oil containment pits
-
Substation lighting
Part 7 — Electrical Installation Works
Includes:
-
MV/HV cable routing
-
HV terminations & joints (certified jointers)
-
Control wiring
-
Optical fibre installation
-
Panel mounting
-
Earthing grid
-
Bus ducting (GIS/AIS)
Part 8 — Testing & Commissioning Requirements
Commissioning follows Clarion’s ITP.
8.1 FAT (Factory Acceptance Tests)
Transformer FAT
GIS/AIS FAT
MV switchgear FAT
Relay configuration FAT
SCADA simulation
Clarion witnesses all Hold Points (H).
8.2 SAT (Site Acceptance Tests)
Visual inspection
Insulation resistance
Ratio/polarity testing
Relay functionality
Interlock checks
8.3 HV Testing
Power-frequency withstand
Partial discharge
Contact resistance
Continuity
Primary & secondary injection
8.4 SCADA & Protection Testing
End-to-end tests
GOOSE/MMS verification
Failover tests
Trip/close sequences
Alarm/event simulation
8.5 Grid Synchronization Tests
Voltage/frequency matching
Reactive control verification
Fault ride-through
PQ compliance
Failure to pass = non-completion.
Part 9 — Documentation
Contractor must provide:
-
AFC design files
-
As-built documentation
-
Cable schedules
-
Relay settings
-
SCADA logic
-
FAT/SAT reports
-
Commissioning records
-
O&M Manuals
-
Spare parts lists
Digital + hard copy required.
Part 10 — Guarantees & Warranty
24-month DLP
5–10 year latent defects
Performance guarantees for:
-
Transformer losses
-
Switchgear availability
-
Protection reliability
-
SCADA uptime
24/7 response team required.
Part 11 — HSE & QA/QC
Contractor must follow Clarion:
-
ITP Matrix
-
QA/QC Manual
-
HSE Plan
-
NCR/CAR system
-
Audit program
-
Lifting plans, method statements, risk assessments
Clarion performs continuous surveillance and signs all Hold Points.
Part 12 — Training & Handover
Training for:
-
Operators
-
Maintenance teams
-
SCADA engineers
-
Protection engineers
Includes:
-
Classroom sessions
-
Hands-on practice
-
Emergency drills
Handover requires:
-
FAC
-
Closed punch list
-
Full documentation
-
Asset register