Clarion Engineers (clarion.engineer) applies a structured, lender-grade EPC execution model tailored for Serbian energy and industrial projects. The framework ensures disciplined governance, technical assurance, strict QA/QC, and controlled commissioning to achieve contractual performance and safe project delivery.
Governance Structure
Owner’s Engineer (Clarion)
-
Technical oversight
-
Compliance checks
-
Review and approval of engineering deliverables
-
Approval of ITP stages
-
Reporting to Employer and lenders
EPC Contractor
-
Full execution responsibility
-
Design, procurement, and construction management
-
Coordination of subcontractors and OEM suppliers
RACI Framework
Responsibility matrix for key EPC activities
| Activity | EPC | Clarion (OE) | Employer | Lenders |
|---|---|---|---|---|
| Design Approval | R | A/C | C | I |
| Procurement Strategy | R | A/C | I | I |
| Quality Control | R | A | I | I |
| Schedule Control | R | A | C | I |
| FAT Witnessing | R | A | I | I |
| Site HSE | R | A (audit) | C | I |
| Performance Tests | R | A | A | I |
| COD & Handover | R | A/C | A | I |
R = Responsible | A = Approver | C = Consulted | I = Informed
Engineering & Design Control
Clarion oversees all critical engineering processes, including:
-
Basis of Design (BoD)
-
Project technical specifications
-
Grid and interconnection studies
-
30/60/90% design reviews
-
OEM integration and interface engineering
-
Compliance with Serbian and EU technical standards
Final engineering must be issued as Approved for Construction (AFC) before site activities begin.
Procurement Management
Clarion’s procurement oversight ensures:
-
OEM and vendor pre-qualification
-
Tracking of long-lead items
-
Full QA/QC documentation compliance
-
Factory Acceptance Tests (FAT) witnessing
-
Shipping, logistics, and customs coordination
Quality Assurance & ITP Framework
Typical ITP stages include:
-
Design review
-
Material certificates and QA documentation
-
Manufacturing inspections
-
FAT
-
Site delivery verification
-
Installation inspections
-
Pre-commissioning testing
-
Performance testing
-
Final acceptance
Clarion participates in and signs off each relevant stage to ensure contractual compliance.
Construction Management
Construction oversight covers:
-
Site establishment and mobilization
-
Civil and structural works
-
Mechanical erection
-
LV/MV/HV electrical works
-
SCADA and system integration
-
Safety audits and inspections
-
Daily reporting and weekly progress reviews
Clarion ensures alignment with schedule, QA/QC standards, and contract requirements.
HSE Management
EPC contractors must implement:
-
HSE Plan
-
Method Statements and Risk Assessments
-
PPE compliance
-
Emergency Response Plan
-
Environmental protection measures
Clarion conducts periodic audits, training sessions, and incident investigations.
Commissioning & Handover
Commissioning activities include:
-
Loop checks and functional verification
-
Cold commissioning
-
Hot commissioning
-
Performance testing under guaranteed conditions
-
Final documentation delivery (as-built drawings, O&M manuals)
-
Training of Employer’s operations team
Clarion witnesses, verifies, and signs off on all major commissioning milestones before COD and handover.